Technical Evaluation Result – Infrastructural development of Lighthouse School Complex – Government Higher Secondary School (GHSS) PEREN under PEREN DISTRICT

  • Version
  • Download 8
  • File Size 161 KB
  • Create Date September 30, 2024
  • Download

NEP-PMU-139/PROC-LSC-PRN/2024                                    
Dated: Kohima, the 30th Sept’ 2024

NOTIFICATION

In response to RFB notice issued vide No IN-DSE-440934-CW-RFB Dated 10th August 2024 for the work “Infrastructural development of Lighthouse School Complex - Government Higher Secondary School (GHSS) Peren under Peren District” the results of the technical evaluation are follows:

 

Sno. Name of Bidder Evaluation Result Reason for disqualification
1 M/S Chabou & Co Qualified  
2 M/S LPSS Infra Qualified  
3 M/S Innovative Constructions Not Qualified Scored below the qualifying score of 60%
4 M/S Z Rulho Not Qualified Scored below the qualifying score of 60%
5 M/S K.Nakhro & Sons (JV KB Enterprise) Not Qualified The bidder participating as a joint venture and did not submit Power of Authority to sign the bid on behalf of the JV firm. Hence considered non-responsive
6 M/S Aien Meren Enterprise Not Qualified The bidder submitted bid security validity for 135 days and the RFB states the validity should be for 165 days.
7 M/S Hexad Syndicate Not Qualified The bidder submitted bid security validity for 120 days and the RFB states the validity should be for 165 days.
8 M/S Naga Construction Not Qualified Does not meet the eligibility and qualification criteria
9 M/S Ensign Constructions Not Qualified Does not meet the eligibility and qualification criteria

 

It is to inform that the opening of the financial bids for the technically qualified bidder is convened at 13:00 Hrs on 3rd October 2024 in the Conference Room, Nagaland Education Project, Directorate of School Education, Kohima for the work “Infrastructural development of Lighthouse School Complex - Government Higher Secondary School (GHSS) Peren under Peren District”

The deadline for requesting debriefing or raising complaints regarding technical evaluation expires at midnight on 2nd October 2024.

This is issued with the approval from the competent authority.

 

(SAMUEL THYUG) NCS
Project Deputy Secretary
Nagaland Education Project