Technical Evaluation Result – Infrastructural development of Lighthouse School Complex- Government Higher Secondary School (GHSS) Bautung Phom Memorial School, Longleng under Longleng District
- Version
- Download 3
- File Size 10 MB
- Create Date November 30, 2024
- Download
NEP-PMU-152/PROC-LSC-LON/2024/834
Dated Kohima, 30th November 2024
NOTIFICATION
In response to RFB notice issued vide No. IN-DSE-454219-CW-RFB dated 8th October 2024, for the work “Infrastructural development of Lighthouse School Complex- Government Higher Secondary School (GHSS) Bautung Phom Memorial School, Longleng under Longleng District”, the result of the Technical Evaluation are as follows:
Name of Bidder | Technical Score (out of 100) | Evaluated Result | Reason for Disqualification |
M/s A Pongshi Phom & Sons | 84.50 | Qualified | |
M/S Jemti Ao | 70.58 | Qualified | |
M/s LPSS Infra | 60.45 | Qualified | |
M/s Savizo Chadi and Co | Not Qualified | Did not meet specific experience criteria | |
M/s Niekho Mere | Not Qualified | Bid security not pledged in favour of Nagaland Education Project Lighthouse |
It is to inform that the opening of the financial bids for the technically qualified bidder will be held on 3rd December 2024 at 11:15 AM in the conference room, Nagaland Education Project, Directorate of school Education, Kohima.
The deadline for raising complaints regarding technical evaluation expires at midnight on 2nd December 2024.
This is issued with approval from competent authority
(AVELU RUHO) NCS
Deputy Project Director
Nagaland Education Project